october 2024

Supreme Court of India · 2024-10-16

Solar Energy Corporation Of India ... vs Wind Four Renergy Private Limited

Citation / case number
2024 INSC 795
Court
Supreme Court of India
Petitioner
Solar Energy Corporation Of India ...
Respondent
Wind Four Renergy Private Limited
Author
Dipankar Datta
Bench
Dipankar Datta

Judgment text excerpt

The Supreme Court upheld the Appellate Tribunal for Electricity's decision to condone a delay of 132 days in the commissioning of a wind power project, emphasizing that the delay was due to the inter-state transmission licensee's failure to operationalize the Long Term Access as required under the Power Purchase Agreement. The Court noted that the Ministry of New & Renewable Energy's letter provided for an extension of 60 days post-operationalization of the LTA, which justified the revised commissioning date. The Court affirmed the Tribunal's order, thereby allowing the extension sought by Wind Four Renergy Private Limited.

Solar Energy Corporation Of India ... vs Wind Four Renergy Private Limited · Niyam