Supreme Court of India · 2024-02-27
Solar Energy Corporation Of India ... vs Wind Four Renergy Private Limited
- Citation / case number
- 2024 INSC 160
- Court
- Supreme Court of India
- Petitioner
- Solar Energy Corporation Of India ...
- Respondent
- Wind Four Renergy Private Limited
- Author
- Dipankar Datta
- Bench
- Dipankar Datta
Judgment text excerpt
The Supreme Court upheld the decision of the Appellate Tribunal for Electricity, which allowed Wind Four Renergy Private Limited's appeal for an extension of the commissioning date of their wind power project. The Court clarified that the delay of 132 days would commence from the date of the APTEL judgment, as per the provisions of the Power Purchase Agreements and the Ministry of New & Renewable Energy's guidelines. The ruling emphasized the importance of timely operationalization of Long Term Access for compliance with project timelines under the relevant agreements.