M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LIMITED(UPNL) vs NORTHERN COAL FIELD LIMITED

Citation / case number
SC 2018/12434
Court
Supreme Court of India
Petitioner
M/S. UTTARAKHAND PURV SAINIK KALYAN NIGAM LIMITED(UPNL)
Respondent
NORTHERN COAL FIELD LIMITED
Author
HON'BLE THE CHIEF JUSTICE
Bench
HON'BLE MS. JUSTICE INDU MALHOTRA HON'BLE THE CHIEF JUSTICE

Judgment text excerpt

The Supreme Court addressed the issue of whether the High Court was correct in rejecting the application for arbitration reference on the grounds of limitation. The Court found that the High Court's decision was not justified as the limitation period for filing the application had not expired. Consequently, the Court allowed the appeal and directed the High Court to refer the matter to arbitration as per the agreement between the parties.