Supreme Court of India · 2019-07-30
Marvel Omega Builders Pvt. Ltd. vs Shrihari Gokhale
- Citation / case number
- AIRONLINE 2019 SC 743
- Court
- Supreme Court of India
- Petitioner
- Marvel Omega Builders Pvt. Ltd.
- Respondent
- Shrihari Gokhale
- Author
- Uday Umesh Lalit
- Bench
- Vineet Saran, Uday Umesh Lalit
Judgment text excerpt
The Supreme Court upheld the National Consumer Disputes Redressal Commission's order under Section 23 of the Consumer Protection Act, 1986, which directed the Appellants to refund Rs.8.14 crores to the Respondents along with 10% simple interest for failure to deliver possession of a residential villa as per the agreement. The Court emphasized that the Appellants could not hold the Respondents responsible for delays caused by Stop Work Notices issued by the Pune Municipal Corporation. The judgment reinforced the obligation of builders to adhere to timelines stipulated in agreements with consumers.