january 2019

Supreme Court of India · 2019-01-23

M/S Shanti Conductors(P) Ltd. vs Assam State Electricity Board and ...

Citation / case number
AIRONLINE 2019 SC 614
Court
Supreme Court of India
Petitioner
M/S Shanti Conductors(P) Ltd.
Respondent
Assam State Electricity Board and ...
Author
Ashok Bhushan
Bench
S.Abdul Nazeer, Ashok Bhushan, A. K. Sikri

Judgment text excerpt

The Supreme Court upheld the applicability of the Interest on Delayed Payment to Small Scale and Ancillary Industrial Undertakings Act, 1993 to contracts entered into prior to its enactment, specifically addressing the maintainability of suits for recovery of interest under the Act. The Court clarified that a suit for recovery of interest is maintainable even if the contract was concluded before the Act came into force. The judgment of the Gauhati High Court was affirmed, allowing the appeal of M/s Shanti Conductors against the Assam State Electricity Board.

M/S Shanti Conductors(P) Ltd. vs Assam State Electricity Board and ... · Niyam