april 2018

Supreme Court of India · 2018-04-05

M.P. Power Management Company Ltd. vs Renew Clean Energy Pvt. Ltd.

Citation / case number
AIR 2018 SUPREME COURT 3632
Court
Supreme Court of India
Petitioner
M.P. Power Management Company Ltd.
Respondent
Renew Clean Energy Pvt. Ltd.
Author
R. Banumathi
Bench
R. Banumathi, Ranjan Gogoi

Judgment text excerpt

The Supreme Court upheld the High Court's decision to set aside the termination of the Power Purchase Agreement (PPA) between M.P. Power Management Company Ltd. and ReNew Clean Energy Private Ltd. The Court found that the appellant's invocation of the bank guarantee under clause 2.5.1 of the PPA was valid, but the termination was unjustified as the respondent had made substantial progress in fulfilling the conditions subsequent. The Court emphasized the need for a fair assessment of the circumstances surrounding the project delays, particularly the challenges faced in land acquisition.

M.P. Power Management Company Ltd. vs Renew Clean Energy Pvt. Ltd. · Niyam