Niyam v2 is live — start for just ₹100 — 200 credits to try

december 2017

Supreme Court of India · 2017-12-05

SUTLEJ CONSTRUCTION LIMITED vs UNION TERRITORY OF CHANDIGARH

Citation / case number
SC 2015/15112
Court
Supreme Court of India
Petitioner
SUTLEJ CONSTRUCTION LIMITED
Respondent
UNION TERRITORY OF CHANDIGARH
Author
SANJAY KISHAN KAUL
Bench
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL HON'BLE MR. JUSTICE J. CHELAMESWAR

Judgment text excerpt

The Supreme Court held that the arbitration award dated 18.12.2013, which partly allowed the appellant's claims and rejected the respondent's counterclaims, was valid and reasoned. The Court found that the Punjab & Haryana High Court erred in setting aside the award, as the termination of the contract by the respondent was not justified under Section 34 of the Arbitration & Conciliation Act, 1996. The Court reinstated the arbitrator's decision, emphasizing the importance of adhering to the arbitration process as stipulated in the contract.

SUTLEJ CONSTRUCTION LIMITED vs UNION TERRITORY OF CHANDIGARH · Niyam