Supreme Court of India · 2016-03-01

Sachichida Nand Prasad & Ors vs Gen.M.,National Thermal Power Corp.& ...

Court
Supreme Court of India
Petitioner
Sachichida Nand Prasad & Ors
Respondent
Gen.M.,National Thermal Power Corp.& ...
Bench
Rohinton Fali Nariman, Kurian Joseph

Judgment text excerpt

The Supreme Court held that the appellants are entitled to a revised land value of Rs. 480/- per decimal, as the High Court's earlier fixation of Rs. 1988/- per decimal was found to be erroneous. The Court directed that if the appellants can demonstrate that similarly situated landowners received higher compensation, they shall also be entitled to that higher rate along with statutory benefits. The Court mandated that the amounts due be paid within three months, thereby ensuring fair compensation for the acquired land under the Land Acquisition Act.

Sachichida Nand Prasad & Ors vs Gen.M.,National Thermal Power Corp.& ... · Niyam