Supreme Court of India · 2016-06-29
M/S. Emm Enn Associates vs Commander Works Engineer & Ors
- Citation / case number
- AIR 2016 SUPREME COURT 3079
- Court
- Supreme Court of India
- Petitioner
- M/S. Emm Enn Associates
- Respondent
- Commander Works Engineer & Ors
- Author
- Ashok Bhushan
- Bench
- Ashok Bhushan, Abhay Manohar Sapre
Judgment text excerpt
The Supreme Court addressed appeals concerning the dismissal of applications for arbitration under Section 11 of the Arbitration and Conciliation Act, 1996. The Court held that the claims made by the contractor were not live claims as they were made after the expiration of the two-year limitation period specified in the contract's Clause 67. Consequently, the Court upheld the High Court's decision, affirming that no arbitrable dispute existed due to the contractor's prior acceptance of the final bill without protest.