Supreme Court of India · 2016-04-22

M/S SHINHAN APEX CORPORATION vs M/S EURO APEX B.V

Citation / case number
SC 2015/3025
Court
Supreme Court of India
Petitioner
M/S SHINHAN APEX CORPORATION
Respondent
M/S EURO APEX B.V
Author
Fakkir Mohamed Ibrahim Kalifulla
Bench
S.A. BOBDE FAKKIR MOHAMED IBRAHIM KALIFULLA

Judgment text excerpt

The Supreme Court addressed the enforcement of an arbitral award under the Arbitration and Conciliation Act, 1996, specifically referencing Section 34. The Court held that the respondent was obligated to transfer patent rights as per the Partial Final Award dated 23.12.2011, and that failure to comply would incur penalties as outlined in the award. The Court affirmed the enforceability of the award, emphasizing the binding nature of arbitration agreements and awards under Indian law.