april 2016

Supreme Court of India · 2016-04-12

PRAGATI BUILDERS & PROMOTERS vs M/S RAM MURTY PYARA LAL & ORS.ETC.

Citation / case number
SC 2012/25204
Court
Supreme Court of India
Petitioner
PRAGATI BUILDERS & PROMOTERS
Respondent
M/S RAM MURTY PYARA LAL & ORS.ETC.
Author
ANIL R. DAVE
Bench
ADARSH KUMAR GOEL ANIL R. DAVE

Judgment text excerpt

The Supreme Court held that the interest awarded by the High Court was insufficient, directing that the appellants receive simple interest at 15% per annum instead of 6% from the date of payment for the property. The Court mandated the respondent bank to calculate and pay the adjusted interest amount to the appellants, while also ensuring the borrower pays the differential interest. The appeals were allowed with no costs, except for the modification of the interest rate.

PRAGATI BUILDERS & PROMOTERS vs M/S RAM MURTY PYARA LAL & ORS.ETC. · Niyam