Niyam v2 is live — start for just ₹100 — 200 credits to try

may 2015

Supreme Court of India · 2015-05-15

M/S GMG ENGINEERING INDUSTRIES vs M/S ISAA GREEN POWER SOLUTION & ORS.

Citation / case number
SC 2013/18651
Court
Supreme Court of India
Petitioner
M/S GMG ENGINEERING INDUSTRIES
Respondent
M/S ISAA GREEN POWER SOLUTION & ORS.
Author
R. BANUMATHI T.S. THAKUR
Bench
R. BANUMATHI T.S. THAKUR

Judgment text excerpt

The Supreme Court upheld the High Court's order requiring the appellants to deposit Rs.1,50,00,000 and Rs.10,00,000 as a condition for condoning the delay in filing applications to set aside ex-parte decrees under Order IX Rule 13 CPC. The Court emphasized that such conditions are within the discretion of the court to ensure that the parties are not allowed to take advantage of their own wrongs. The appeals were dismissed, affirming the lower court's decision and the necessity of compliance with the imposed conditions.

M/S GMG ENGINEERING INDUSTRIES vs M/S ISAA GREEN POWER SOLUTION & ORS. · Niyam