Supreme Court of India · 2014-09-05

M/S. Harsha Constructions vs Union Of India & Ors

Citation / case number
AIR 2015 SUPREME COURT 270
Court
Supreme Court of India
Petitioner
M/S. Harsha Constructions
Respondent
Union Of India & Ors
Bench
Vikramajit Sen, Anil R. Dave

Judgment text excerpt

The Supreme Court addressed the issue of whether an arbitrator can arbitrate on disputes that are expressly excepted in a contract, specifically under Clause 63 of the contract between M/s Harsha Constructions and the Union of India. The Court held that matters deemed as 'Excepted matters' under the contract, which include specific clauses, are excluded from arbitration and must be resolved through the specified decision-making process. Consequently, the appeal was dismissed, affirming the High Court's ruling that the arbitrator lacked jurisdiction over the excepted issues.