may 2014

Supreme Court of India · 2014-05-08

G. Sundarrajan vs U.O.I & Ors

Citation / case number
AIRONLINE 2014 SC 448
Court
Supreme Court of India
Petitioner
G. Sundarrajan
Respondent
U.O.I & Ors
Author
K.S. Radhakrishnan
Bench
Vikramajit Sen, K.S. Radhakrishnan

Judgment text excerpt

The Supreme Court addressed compliance issues related to its earlier judgment in G. Sundarrajan vs. Union of India, directing various authorities including AERB and NPCIL to adhere to 15 specific directions regarding the Kudankulam Nuclear Power Project. The Court emphasized the necessity of independent verification of compliance before commissioning the plant, particularly concerning safety and quality of equipment. The Court held that the affidavits submitted by AERB and NPCIL demonstrated substantial compliance with the directions, thereby allowing the project to proceed under strict regulatory oversight.