october 2012

Supreme Court of India · 2012-10-18

Ratnagiri Gas & Power Pvt.Ltd vs Rds Projects Ltd.& Ors

Citation / case number
AIR 2013 SC (CIVIL) 2330
Court
Supreme Court of India
Petitioner
Ratnagiri Gas & Power Pvt.Ltd
Respondent
Rds Projects Ltd.& Ors
Author
T.S. Thakur
Bench
Gyan Sudha Misra, T.S. Thakur

Judgment text excerpt

The Supreme Court upheld the High Court's order quashing the rejection of RDS Project Ltd.'s tender for the construction of a breakwater at the LNG Terminal, emphasizing the need for a fair evaluation process in public procurement. The Court reiterated that the tender conditions, particularly Clause 8.1.1.1, must be interpreted in a manner that does not unjustly exclude capable bidders. The Court directed the appellant, Ratnagiri Gas & Power Pvt. Ltd., to reconsider the tender in light of the High Court's observations, thereby reinforcing principles of transparency and fairness in administrative actions.

Ratnagiri Gas & Power Pvt.Ltd vs Rds Projects Ltd.& Ors · Niyam