Supreme Court of India · 2012-04-09

Premji Nathu vs State Of Gujarat & Anr

Citation / case number
AIR 2012 SUPREME COURT 1624
Court
Supreme Court of India
Petitioner
Premji Nathu
Respondent
State Of Gujarat & Anr
Author
G.S. Singhvi
Bench
G.S. Singhvi, Sudhansu Jyoti Mukhopadhaya

Judgment text excerpt

The Supreme Court addressed the issue of whether the application under Section 18(1) of the Land Acquisition Act, 1894 was time-barred. The Court held that the Reference Court correctly determined that the applications were beyond the time limit specified in Section 18(2)(b) of the Act, thus denying the enhancement of compensation. The Court affirmed the lower court's decision, emphasizing the importance of adhering to statutory timelines in land acquisition matters.