Supreme Court of India · 2011-01-17
ZUARI CEMENTS LTD. vs A.P.POWER GENERATION CORP.LTD..
- Citation / case number
- SC 2010/25792
- Court
- Supreme Court of India
- Petitioner
- ZUARI CEMENTS LTD.
- Respondent
- A.P.POWER GENERATION CORP.LTD..
- Author
- R.V. RAVEENDRAN,A.K. PATNAIK, , ,
- Bench
- R.V. RAVEENDRAN,A.K. PATNAIK, , ,
Judgment text excerpt
The Supreme Court modified the interim order regarding the supply of fly ash, directing that the appellants pay Rs.250/- per metric tonne instead of Rs.90/- during the pendency of the writ petitions. The Court held that the appellants must make payments based on the provisional rate and will be liable for any price difference if they lose the writ petitions. The decision emphasizes the need for an interim arrangement to serve the interests of justice while the main issues are pending resolution.