Niyam v2 is live — start for just ₹100 — 200 credits to try

july 2010

Supreme Court of India · 2010-07-09

CONTROLLER,VINAYAK MISSION DEN.COL. vs GEETIKA KHARE

Citation / case number
SC 2009/29180
Court
Supreme Court of India
Petitioner
CONTROLLER,VINAYAK MISSION DEN.COL.
Respondent
GEETIKA KHARE
Author
MARKANDEY KATJU,T.S. THAKUR, , ,
Bench
MARKANDEY KATJU,T.S. THAKUR, , ,

Judgment text excerpt

The Supreme Court held that the refund of the fee deposited by the respondent with interest at 12% per annum from 31st July 2000 till the date of payment was sufficient to meet the ends of justice. The Court found that the National Commission's reduction of compensation to Rs. 2,50,000 was unwarranted, as the respondent had already received Rs. 5,15,000 with interest. The Court set aside the directions for further compensation, affirming that the claim was settled with the amount already received by the respondent.

CONTROLLER,VINAYAK MISSION DEN.COL. vs GEETIKA KHARE · Niyam