The Supreme Court allowed the review petitions and clarified the conditions for extension of the project implementation period as per the terms in the letters of allotment. The Court held that the respondents must deposit the required amount within six weeks and the appellant must hand over possession of the plot within four weeks thereafter. The ruling emphasized that failure to comply with payment terms would allow the appellant to take legal recourse, thereby reinforcing the contractual obligations under the allotment agreement.