Supreme Court of India · 2009-04-01
Ahmmadsahab Abdul Mulla (D) By Prop. Lrs vs Bibijan & Ors
- Citation / case number
- AIR 2009 SUPREME COURT 2193
- Court
- Supreme Court of India
- Petitioner
- Ahmmadsahab Abdul Mulla (D) By Prop. Lrs
- Respondent
- Bibijan & Ors
- Author
- Arijit Pasayat
- Bench
- Asok Kumar Ganguly, Harjit Singh Bedi, Arijit Pasayat
Judgment text excerpt
The Supreme Court addressed the interpretation of 'date' in Article 54 of the Limitation Act, 1963, clarifying that it does not necessarily imply a specific calendar date but can be determined based on the circumstances of the case. The Court noted differing interpretations by various High Courts and referenced previous judgments, including Ramzan v. Hussaini and Tarlok Singh v. Vijay Kumar Sabharwal, to establish that the date for performance in a contract may be contingent upon certain events. The Court ultimately held that a purposive interpretation should be applied to the term 'date fixed' in the context of specific performance claims.