Niyam v2 is live — start for just ₹100 — 200 credits to try

march 2008

Supreme Court of India · 2008-03-14

M/S. GRINDWELL NORTON LTD. vs M/S. MAXLUX GLASS PVT. LTD. .

Citation / case number
SC 2007/11768
Court
Supreme Court of India
Petitioner
M/S. GRINDWELL NORTON LTD.
Respondent
M/S. MAXLUX GLASS PVT. LTD. .
Bench
S.B. SINHA & V.S. SIRPURKAR

Judgment text excerpt

The Supreme Court addressed procedural irregularities by the Magistrate in preponing the date of a hearing from 17.2.2000 to 1.2.2000, stating that while the manner was not approved, the subsequent events justified a remedy. The Court held that the respondent should pay an additional sum of Rupees Fifty Thousand to the appellant in each case, emphasizing the need to serve the interests of justice. The appeals were allowed with this direction, and no costs were imposed.

M/S. GRINDWELL NORTON LTD. vs M/S. MAXLUX GLASS PVT. LTD. . · Niyam