The Supreme Court condoned the delay in depositing 50% of the enhanced compensation as required under Section 18 of the Land Acquisition Act, 1894, and directed the High Court to accept the deposit. The Court held that the stay granted on 04/01/2007 would continue until the disposal of the appeal before the High Court, thereby ensuring the claimants could withdraw the deposited amount without security. The appeal was disposed of without costs.