Niyam v2 is live — start for just ₹100 — 200 credits to try

april 2008

Supreme Court of India · 2008-04-10

UNION OF INDIA vs CHANDALAVADA GOPALAKRISHNA MURTHY .

Citation / case number
SC 2001/14290
Court
Supreme Court of India
Petitioner
UNION OF INDIA
Respondent
CHANDALAVADA GOPALAKRISHNA MURTHY .

Judgment text excerpt

The Supreme Court held that under Clause 17(3) of the contract, if there is a delay caused by the Railway, the contractor is not entitled to damages or compensation, but may receive an extension of the completion date. The Court reaffirmed the principle established in Ch. Ramalinga Reddy Vs. Superintending Engg. & Anr. (1999) and General Manager (Northern Railway) Vs. Sarvesh Chopra (2002), stating that compensation cannot be awarded if the contract is extended under its terms. Consequently, the order of the Andhra Pradesh High Court was set aside, and the appeals were allowed without costs.

UNION OF INDIA vs CHANDALAVADA GOPALAKRISHNA MURTHY . · Niyam