Supreme Court of India · 2007-04-10

F.C.I. vs M/S. CHANDU CONSTRUCTION

Citation / case number
SC 2006/1610
Court
Supreme Court of India
Petitioner
F.C.I.
Respondent
M/S. CHANDU CONSTRUCTION
Author
D.K. JAIN TARUN CHATTERJEE
Bench
D.K. JAIN TARUN CHATTERJEE

Judgment text excerpt

The Supreme Court upheld the arbitration award of Rs. 8,23,101/- in favor of the claimants, affirming that the contract terms included the cost of materials, specifically sand, as part of the work scope. The Court clarified that the claimants were entitled to additional payment for supplying sand, as the original tender only covered labor costs. The judgment emphasized the binding nature of the arbitration agreement and the arbitrator's authority to interpret contract terms under the Arbitration and Conciliation Act, 1996.