Niyam v2 is live — start for just ₹100 — 200 credits to try

october 2005

Supreme Court of India · 2005-10-25

STATE OF KARNATAKA vs LAXUMAN

Citation / case number
SC 1998/20204
Court
Supreme Court of India
Petitioner
STATE OF KARNATAKA
Respondent
LAXUMAN
Author
R.C. LAHOTI,G.P. MATHUR,P.K. BALASUBRAMANYAN
Bench
CJI R.C. LAHOTI,G.P. MATHUR,P.K. BALASUBRAMANYAN

Judgment text excerpt

The Supreme Court addressed the interpretation of Section 18 of the Land Acquisition Act, particularly regarding the application for condonation of delay under Section 18(3)(b). The Court held that the application for reference must be made within three years of the expiry of the initial 90-day period, and that Section 5 of the Limitation Act applies to such applications. The Court ultimately upheld the High Court's decision to condone the delay, emphasizing the necessity of adhering to procedural timelines while ensuring justice is served.

STATE OF KARNATAKA vs LAXUMAN · Niyam