M/S CONTINENTAL CONSTRUCTION LTD. vs STATE OF U .P.

Citation / case number
SC 1997/10180
Court
Supreme Court of India
Petitioner
M/S CONTINENTAL CONSTRUCTION LTD.
Respondent
STATE OF U .P.
Bench
CJI & S.B. SINHA.

Judgment text excerpt

The Supreme Court addressed the arbitration dispute arising from a contract for the construction of the Obra dam, specifically regarding claims for extra quantities of earth and rock. The Court held that the appellant's claims for additional compensation were valid under the arbitration agreement, and the previous decisions by the lower courts that set aside the arbitrator's awards were incorrect. The Court reinstated the awards made by the Umpire, emphasizing the enforceability of arbitration agreements under the Arbitration Act, 1940, particularly Sections 30 and 33.