Apex Engg. Pvt. Ltd. And Anr. vs Fair Growth Financial Services Ltd. And ...

Citation / case number
AIR 2002 SUPREME COURT 2542
Court
Supreme Court of India
Petitioner
Apex Engg. Pvt. Ltd. And Anr.
Respondent
Fair Growth Financial Services Ltd. And ...
Bench
B.N. Kirpal, N. Santosh Hegde, P. Venkatarama Reddi

Judgment text excerpt

The Supreme Court held that the hire-purchase agreement between Apex Engineering Pvt. Ltd. and Fair Growth Financial Services Limited required full payment of Rs. 56.21 lakhs, which was ultimately paid, albeit with a delay. The Court modified the decree of the Special Court, ruling that an additional payment of Rs. 32,64,142.70 made under interim orders should be considered as full and final payment. Furthermore, it directed Fair Growth to transfer the title of the wheel loaders to Apex Engineering upon payment of a nominal price of Re. 1.

Apex Engg. Pvt. Ltd. And Anr. vs Fair Growth Financial Services Ltd. And ... · Niyam