Supreme Court of India · 2001-12-04

WEST BENGAL STATE ELECTRICITY BOARD vs CALCUTTA ELECTRIC SUPPLY CORPN. LTD.

Citation / case number
SC 2001/10117
Court
Supreme Court of India
Petitioner
WEST BENGAL STATE ELECTRICITY BOARD
Respondent
CALCUTTA ELECTRIC SUPPLY CORPN. LTD.
Author
RUMA PAL G.B. PATTANAIK
Bench
RUMA PAL G.B. PATTANAIK

Judgment text excerpt

The Supreme Court ruled that under Section 44 of the Electricity (Supply) Act, 1948, a licensee must obtain prior consent from the Board before establishing a new generating station. The Court held that the Board's consent for the Budge Budge Project was valid despite subsequent cost escalations, as the licensee had complied with the necessary procedural requirements. The judgment affirmed the importance of adhering to statutory provisions for project approvals in the electricity sector.