Supreme Court of India · 2001-08-07
The Project Officer vs Vs
- Court
- Supreme Court of India
- Petitioner
- The Project Officer
- Respondent
- Vs
- Bench
- S. Rajendra Babu, Doraiswamy Raju
Judgment text excerpt
The Supreme Court addressed the issue of compensation for land acquired by the Singareni Colleries Company Limited, where the Land Acquisition Officer initially set the market value significantly lower than the civil court's enhancement. The Court held that the appellants, not being parties to the civil court proceedings, were entitled to challenge the enhanced compensation order. The Court set aside the High Court's interim stay on the civil court's order, emphasizing that the appellants' writ petition should be heard alongside the appeal filed by the Land Acquisition Officer before any compensation payment is enforced.