Niyam v2 is live — start for just ₹100 — 200 credits to try

november 2000

Supreme Court of India · 2000-11-08

Bihar State Electricity Board & Anr vs Umi Special Steel Limited

Citation / case number
AIR 2001 SUPREME COURT 161
Court
Supreme Court of India
Petitioner
Bihar State Electricity Board & Anr
Respondent
Umi Special Steel Limited
Author
S. N. Variava
Bench
V N Khare, S.N. Variava

Judgment text excerpt

The Supreme Court addressed the enforceability of a contract for the supply of electricity under the terms of the Agreement dated 12th January 1972, specifically focusing on Clauses 4(a), 8, and 9. The Court held that the consumer could not unilaterally terminate the Agreement before the expiration of three years, and any determination thereafter required a twelve-month notice. The Court ruled that the Respondent's request to terminate the Agreement was not valid as it did not comply with the stipulated notice period, thus upholding the lower court's dismissal of the appeal.

Bihar State Electricity Board & Anr vs Umi Special Steel Limited · Niyam