july 1996

Supreme Court of India · 1996-07-09

SECY. TO GOVT. OF KARNATAKA vs V. HARISHBABU

Citation / case number
SC 1995/13811
Court
Supreme Court of India
Petitioner
SECY. TO GOVT. OF KARNATAKA
Respondent
V. HARISHBABU
Author
A.S. ANAND
Bench
A.S. ANAND

Judgment text excerpt

The Supreme Court addressed the commencement of the limitation period for filing objections to an arbitration award under the Indian Arbitration Act, specifically referencing Section 14 and Section 17. The Court held that the limitation period begins from the date the award is made known to the parties, and in this case, the appellant failed to file objections within the prescribed 30 days, leading to the award being made a rule of the court. The appeal was dismissed as the appellant did not comply with the statutory timeline for objections.