PUNE CANTONMENT BOARD vs M.P.J. BUILDERS

Citation / case number
SC 1995/1585
Court
Supreme Court of India
Petitioner
PUNE CANTONMENT BOARD
Respondent
M.P.J. BUILDERS
Author
S. VERMA
Bench
JAGDISH SARAN VERMA

Judgment text excerpt

The Supreme Court addressed the validity of a building sanction under Section 181 of the Cantonments Act, 1924, where the respondent failed to complete construction within the stipulated time. The Court held that the failure to complete the building within the prescribed period, coupled with the absence of a timely extension request, resulted in the lapse of the building sanction. Consequently, the Court ruled that the respondent's applications for extension made after the deadline were ineffective, affirming the lower court's decision to deny the extension.