Supreme Court of India · 1995-11-10

STATE OF U.P. vs RAM NATH INTERNATIONAL CONSTRUCTION

Citation / case number
SC 1994/4600
Court
Supreme Court of India
Petitioner
STATE OF U.P.
Respondent
RAM NATH INTERNATIONAL CONSTRUCTION
Author
PATTANAIK
Bench
G.B. PATTANAIK

Judgment text excerpt

The Supreme Court upheld the arbitration award in favor of the contractor, affirming that under the Arbitration and Conciliation Act, 1996, the contractor was entitled to claim enhanced rates due to substantial changes in designs and drawings that resulted in an abnormal increase in work quantity. The Court emphasized that the contractor's claim was justified as the changes were significant enough to warrant a revision of rates, despite the State's contention based on the original agreement. The judgment reinforced the principle that parties must adhere to the terms of the contract while also recognizing the need for equitable adjustments in cases of unforeseen changes.

STATE OF U.P. vs RAM NATH INTERNATIONAL CONSTRUCTION · Niyam