march 1988

Supreme Court of India · 1988-03-07

CONTINENTAL CONSTRUCTION CO. LTD. vs STATE OF MADHYA PRADESH

Citation / case number
SC 1985/66944
Court
Supreme Court of India
Petitioner
CONTINENTAL CONSTRUCTION CO. LTD.
Respondent
STATE OF MADHYA PRADESH
Author
SABYASACHI MUKHARJI
Bench
SABYASACHI MUKHARJI

Judgment text excerpt

The Supreme Court held that under the Arbitration Act, 1940, a contractor cannot claim extra costs due to delays caused by the other party unless specific legal questions are referred to the arbitrator. The Court found that the arbitrator had misconducted himself by allowing claims without addressing the State's objections, and thus the award was set aside. The Court emphasized that the arbitrator must adhere to the law and cannot ignore contractual obligations, affirming the District Judge's decision to reject the contractor's claims for extra costs.