january 1969

Supreme Court of India · 1969-01-29

SIHOR ELECTRICITY WORKS LTD. vs THE GUJARAT ELECTRICITY BOARD AND ANR.

Citation / case number
SC 1966/60380
Court
Supreme Court of India
Petitioner
SIHOR ELECTRICITY WORKS LTD.
Respondent
THE GUJARAT ELECTRICITY BOARD AND ANR.
Bench
RAMASWAMI

Judgment text excerpt

The Supreme Court held that under Section 2(8) and Section 19(1)(b)(ii) of the Electricity (Supply) Act, 1948, the 'maximum demand' must relate to an existing state of facts and cannot be based on hypothetical future demands. The Court found that the comparison for direct supply eligibility must be made between the actual maximum demand of the licensee at the time of request and the demand of the applicant, not anticipated future demands. The Court upheld the trial court's decree, ruling that the first respondent's decision to grant direct supply was ultra vires.