M/S VISHAL INFRASTRUCTURE LTD. AND M/S OJSC EURO - ASIAN CONSTRUCTION CORPORATION EVRASCON (JV) vs CHIEF ENGINEER (CONST)-I, NORTH WESTERN RAILWAY, JAIPUR

Citation / case number
O.M.P.(I) (COMM.)-220/2026 2026:DHC:4801
Court
Delhi High Court
Petitioner
M/S VISHAL INFRASTRUCTURE LTD. AND M/S OJSC EURO - ASIAN CONSTRUCTION CORPORATION EVRASCON (JV)
Respondent
CHIEF ENGINEER (CONST)-I, NORTH WESTERN RAILWAY, JAIPUR
Search all judgments

Judgment text excerpt

IN THE HIGH COURT OF DELHI AT NEW DELHI Date of Decision: 26.05.2026 + O.M.P.(I) (COMM.) 220/2026, I.A. 14558/2026 (EX. From filing original/typed copies of the documents), I.A. 14559/2026 (Seeking permission to file lengthy synopsis and list of dates) & I.A. 14560/2026 (Ex. From filing translated copies of the documents) M/S VISHAL INFRASTRUCTURE LTD. AND M/S OJSC EURO - ASIAN CONSTRUCTION CORPORATION EVRASCON (JV) .....Petitioner Through: Mr. Sonal Kumar Singh, Mr. Ratik Sharma, Ms. Muskan Agarwal, Mr. Parth Sindhwani and Mr. Yashvadhan Singh Gohil, Advocates versus CHIEF ENGINEER (CONST)-I, NORTH WESTERN RAILWAY, JAIPUR .....Respondent Through: Mr. Siddhartha Shankar Ray, CGSC, Mr. Manish Rawat, GP, Ms. Sonali Modi, Ms. Shrishti Singh, Ms. Vatsala Shukla and Mr. Mohit Bokoliya, Advocates CORAM: HON'BLE MR. JUSTICE HARISH VAIDYANATHAN SHANKAR % JUDGEMENT (ORAL) 1. The present Petition, under Section 9 of the Arbitration and Conciliation Act, 1996, seeks the following reliefs: “a. Pass an ex-parte ad-interim stay/restraining the Respondent from acting pursuant to, or taking any coercive steps in furtherance of the Notice intimating intent to terminate the EPC Agreement awarded to