Delhi High Court · 2026-04-07
MS. STALAGMITE INFRACON PVT vs MS. ASHRAY HOMES BUILD WELL PVT
- Citation / case number
- O.M.P. (COMM)-367/2019 2026:DHC:2890
- Court
- Delhi High Court
- Petitioner
- MS. STALAGMITE INFRACON PVT
- Respondent
- MS. ASHRAY HOMES BUILD WELL PVT
Judgment text excerpt
$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on: 27th March, 2026 Pronounced on: 07th April, 2026 + O.M.P. (COMM) 367/2019 & I.A. 12495/2019, I.A. 12496/2019 MS. STALAGMITE INFRACON PVT. LTD. .....Petitioner Through: Mr. Sundeep Sehgal, Adv. Mob: 9810005572 Email: [email protected] versus MS. ASHRAY HOMES BUILD WELL PVT. LTD. .....Respondent Through: Mr. Manu Aggarwal and Ms. Ishita Pandey, Advs. Mob: 9810007854 Email: [email protected] CORAM: HON'BLE MS. JUSTICE MINI PUSHKARNA JUDGEMENT MINI PUSHKARNA, J. I.A. 12495/2019 & I.A. 12496/2019 1. The present petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”), seeking to set aside the impugned interim Arbitral Award dated 28th January, 2019, to the extent of findings therein which are against the petitioner. 2. I.A. 12495/2019 has been filed by the petitioner seeking condonation of delay of 30 days in filing the present petition, and I.A. 12496/2019 has been filed seeking condonation of delay of 90 days in re-filing the present petition. 3. The disputes between the parties herein had arisen in relation to the Memorandum of Understanding dated 12th March, 2015 (“MoU”)