Delhi High Court · 2025-05-15
DELHI DEVELOPMENT AUTHORITY vs GAMMON ENGINEERS AND CONTRACTORS PVT LTD
- Citation / case number
- FAO(OS) (COMM)-87/2025 2025:DHC:3864-DB
- Court
- Delhi High Court
- Petitioner
- DELHI DEVELOPMENT AUTHORITY
- Respondent
- GAMMON ENGINEERS AND CONTRACTORS PVT LTD
Judgment text excerpt
IN THE HIGH COURT OF DELHI AT NEW DELHI Date of decision: 15.05.2025 + FAO(OS) (COMM) 87/2025 DELHI DEVELOPMENT AUTHORITY .....Appellant Through: Mr.Kailash Vasdev, Sr. Adv. with Mr.Rajeev Lochan Mahunta, Mr.Pratyush Mishra, Ms.Neoma Vasdev, Mr.Umrao Singh Rawat and Ms.Ashtha Bhardwaj, Advs. versus GAMMON ENGINEERS AND CONTRACTORS PVT LTD .....Respondent Through: None CORAM: HON'BLE MR. JUSTICE NAVIN CHAWLA HON'BLE MS. JUSTICE RENU BHATNAGAR NAVIN CHAWLA, J. (ORAL) FAO(OS) (COMM) 87/2025 & CM APPL. 27543/2025 1. This appeal has been filed by the appellant under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as, ‘the Act’), challenging the order dated 26.07.2024 passed by the learned Single Judge of this Court in O.M.P.(COMM)128/2023, titled Delhi Development Authority v. Gammon Engineers and Contractors Private Limited (Gammon), dismissing the said 2. It is not denied that the Award impugned before the learned Single Judge in form of the above application was passed on 15.11.2021. A copy of the same was received by the appellant on 22.11.2021, whereafter the appellant filed the above-mentioned application under Section 34 of the Act, on 14.03.2022