High Court of Andhra Pradesh · 2025-03-06
WP/2662/2025 of PEDDISETTY GURAVAIAH Vs THE STATE OF ANDHRA PRADESH
- Citation / case number
- APHC010046622025
- Court
- High Court of Andhra Pradesh
- Petitioner
- WP/2662/2025 of PEDDISETTY GURAVAIAH
- Respondent
- THE STATE OF ANDHRA PRADESH
Judgment text excerpt
HIGH COURT OF ANDHRA PRADESH :: AMARAVATI MAIN CASE: W.P.No.26662 of 2025 PROCEEDING SHEET Sl. OFFICE No. DATE ORDER NOTE 7. 25.02.2026 NJS, J I.A.No.2 of 2026 Heard Mr.Dore Raj B.H., learned arguing counsel for the petitioner. Considering the submissions made and perusing the orders dated 17.10.2025 and 04.02.2026, this Court is inclined to grant interim orders. Accordingly, there shall be a direction to the respondent Nos.1 and 2 not to take any coercive action of disconnection of power supply to the petitioner-Industry, pursuant to the Bill dated 03.02.2026, subject to the petitioner paying Rs.11 lakhs, within a period of six (6) weeks from today. List this case on 01.04.2026 ______ NJS, J Note: Furnish C.C. today. B/o. BLV