Bombay High Court · 2025-04-09

KARAM CHAND THAPAR AND BROS. (COAL SALES) LTD. AND ANR vs MAHARASHTRA STATE POWER GENERATION COMPANY LTD AND 2 ORS AND SENDOZ COMM.PVT LTD AND ANR (PROP RES)

Citation / case number
IAL/17609/2024
Court
Bombay High Court
Petitioner
KARAM CHAND THAPAR AND BROS. (COAL SALES) LTD. AND ANR
Respondent
MAHARASHTRA STATE POWER GENERATION COMPANY LTD AND 2 ORS AND SENDOZ COMM.PVT LTD AND ANR (PROP RES)

Judgment text excerpt

3590.24-wp.docx IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION NO.3590 OF 2024 Digitally signed by Karam Chand Thapar & Bros. BASAVRAJ BASAVRAJ GURAPPA (Coal Sales) Ltd. & Anr. ….. Petitioners GURAPPA PATIL PATIL Date: 2025.04.09 Vs. 19:02:53 +0530 Maharashtra state Power Generation Co. Ltd. & Ors. ….. Respondent WITH INTERIM APPLICATION (L) NO.17609 OF 2024 IN WRIT PETITION NO.3590 OF 2024 Karam Chand Thapar & Bros. (Coal Sales) Ltd & Anr. ….. Applicants Vs. Maharashtra state Power Generation Co. Ltd. & Ors. ….. Respondents Mr. Zal Andhyarujina, Senior Advocate with Ms. Ishani Khanwilkar, Mr. Munaf virjee, Mr. Tirtha Mukherjee i/b. AMR Law for the petitioners Dr. Birendra Saraf, Senior Advocate with Ms. Amita Chaware for respondent No.1 and 2 Ms. Jyoti Chavan, Additional Government Pleader with Ms. Nazia Sheikh, AGP for respondent No.3 – State Ms. Saloni Manjrekar i/b. HH Legal for respondent No.4 Ms. Nikita Bhansali a/w. Mr. Tejas Gupta and Ms. Roshni Bhati i/b. Yasmin Bhansali & Co. for respondent No.5 CORAM: ALOK ARADHE, CJ. & M. S. KARNIK, J. RESERVED ON : APRIL 7, 2025 PRONOUNCED ON : APRIL 9, 2025 Basavraj Page | 1 3590.24-wp.docx JUDGMENT (PER : CHIEF JUSTICE) Rule. Rule is made returnable forthwith. By consent of the learned counsel for the parties, heard finally. 2. The Karam Chand Thapar & Bros. (Coal Sales) Ltd. (petitioner) is a company, engaged in the business of liaisoning, movement, handling and delivery of raw coal from Coalfields to Thermal Power stations by by rail as well as rail-sea route. Mr. Sampat Shete is the Director of the petitioner. (A) CHALLENGE: 3. In this petition, the bid of the petitioner has been rejected by the Chief Engineer (Fuel Management) MAHAGENCO (Chief Engineer). The petitioners ha

KARAM CHAND THAPAR AND BROS. (COAL SALES) LTD. AND ANR vs MAHARASHTRA STATE POWER GENERATION COMPANY LTD AND 2 ORS AND SENDOZ COMM.PVT LTD AND ANR (PROP RES) · Niyam