## Judgment text (excerpt)

Arb O.P(COM.DIV.) SR No. 7918 of 2026 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 15-07-2026 CORAM THE HON'BLE MR.JUSTICE K.KUMARESH BABU Arb O.P(COM.DIV.) SR No. 7918 of 2026 and A.No.2391 of 2026 The Union of India, Represented by the Chief Engineer(CG) D No.39-4-2/2, Plot no.18, Near Varma Complex, Murali Nagar, Visakhapatnam – 530 007. ..Petitioner(s) Vs M/s.Suma Encon Projects Pvt Ltd No; 1-83-14/2, Plot No.4, Second Floor, Sector-3, MVP Double Road, MVP Colony, Visakhapatnam – 530 017. ..Respondent(s) Petition filed under Section 34 (2 & 3) of the Arbitration and Conciliation Act, 1996, prays that this Hon’ble Court maybe pleased; (a) To set aside the Arbitral Award dated 30.06.2025 bearing Agreement No CE (NAVY)/VIZ/CHN/10 OF 2017-18 passed by Shri Arvind Kumar Arora, Sole Arbitrator for claim No 1 and interest thereof to the extent to which it is challenged. (b) To direct the respondent to pay the costs; and (c) To grant such further relief as this Hon’ble Court may deem fit under the circumstances of the case and thus render justice. For Petitioner(s): Mr.K.Kannan For Respondent(s): Mr.P.J.Rishikesh __________ Page1 of 4 https://www.mhc.tn.gov.in/judis ( Uploaded on: 

https://niyam.ai/judgements/high-court/2026/july/the-union-of-lndia-represented-by-chief-engineer-vs-suma-encon-projects-pvt-ltd