IN THE HIGH COURT OF DELHI AT NEW DELHI Date of Decision: 06th January, 2026 + O.M.P.(I) (COMM.) 6/2026 & I.A. 289/2026 M/S KGK ENGINEERS PVT LTD .....Petitioner Through: Mr. K. Shiva, Advocate (M: 8489662301) (Email:shivakrishnamurti@gmail.com) versus NATIONAL HIGHWAYS AUTHORITY OF INDIA NHAI & ANR. .....Respondents Through: Mr. Manish K. Bishnoi, Mr. Khubaib Shakeel, Advocates for NHAI (M:7006913529) Email: kskhubaib07@gmail.com CORAM: HON'BLE MS. JUSTICE MINI PUSHKARNA MINI PUSHKARNA, J (ORAL): 1. The present petition has been filed under Section 9 (1) (ii) (e) of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”) seeking injunction for restraining the respondent no.1 from terminating the Contract Agreement dated 30th June, 2023 executed between the parties, and consequently restraining the respondents from invoking the Bank Guarantees provided by the petitioner. 2. As per the case put forth by the petitioner, the petitioner had emerged as the successful bidder in the „Request For Proposal‟ (“RFP”) for permanent rectification of black spot by construction of a light vehicular 2024. 3. As per Clause 7 of the Contract Agreement dated 30th June, 2023, between the partie

https://niyam.ai/judgements/high-court/2026/january/m-s-kgk-engineers-pvt-ltd-vs-national-highways-authority-of-india-nhai-anr