# APPEAL UNDER SECTION 37 OF ARBITRATION AND CONCILIATION ACT 1996 No. 24 of 2025 at Allahabad

Court: Allahabad High Court
Date: 2025-07-08
Citation: APPEAL UNDER SECTION 37 OF ARBITRATION AND CONCILIATION ACT 1996 No. 24 of 2025 at Allahabad
Petitioner: APPEAL UNDER SECTION 37 OF ARBITRATION AND CONCILIATION ACT 1996 No. 24 of 2025 at Allahabad
Respondent: Unknown

[Official PDF on Allahabad High Court website](https://elegalix.allahabadhighcourt.in/elegalix/WebDownloadOriginalHCJudgmentDocument.do?translatedJudgmentID=41398)

## Judgment text (excerpt)

Neutral Citation No. - 2025:AHC:108029-DB Chief Justice's Court Case :- APPEAL UNDER SECTION 37 OF ARBITRATION AND CONCILIATION ACT 1996 No. - 24 of 2025 Appellant :- M/s Raj Construction Company Respondent :- North Central Railway Allahabad and another Counsel for Appellant :- Anubhav Chandra, Surabhi Chandra Counsel for Respondent :- A.S.G.I., Krishna Agarawal Hon'ble Arun Bhansali, Chief Justice Hon'ble Kshitij Shailendra, J. 1. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, 'the Act') is directed against order dated 11.09.2024 passed by Commercial Court No. 1, Agra whereby the application filed by the appellant under Section 34 of the Act against award dated 20.01.2024 has been dismissed. 2. The appellant is engaged in the business of civil construction. The respondents floated e-Tender for Runakta, Kitham improvement to station approach, platform surface, COP and toilet facilities on both platforms with provision for physically challenged amenities. 3. The appellant participated in the tender and Letter of Acceptance was issued to him, whereafter agreement was also executed. It is claimed that the appellant completed the work at Kitham s